Narito ang mga proyekto ng PNOY Administration na makukumpleto na sa Duterte administration

Duterte-Aquino_VivaPinas

Duterte-Aquino_VivaPinas

Project NameDescriptionTarget date of completion
NCR
NAIA Expressway, Phase IIA 4.70-km , four-lane elevated expressway from Sales Road to MIA Road; will reduce average travel time between Skyway and NAIA Terminal 1November 2016 (75% complete as of April 2016)
CAMARINES SUR
Tignon-Goa-San Jose-Lagonoy-Guijalo Tourism RoadWill reduce travel time between Naga City and Caramoan; an access road to Caramoan Island, a tourist destination in Camarines SurJuly 2016
Naga Airport, Naga CityExpansion and improvement of passenger terminal building to provide wider space for passengers and improve service deliveryOctober 2016
ALBAY
Tabaco Port, Tabaco CityExpansion of reinforced concrete wharf and construction of backup area to provide wider space for vessels and passengersAugust 2016 (81% as of April 2016)
Rehabilitation of damaged wharfNovember 2016 (34% as of April 2016)
Legazpi Base Port, Legazpi CityRehabilitation and upgrade of damaged wharfDecember 2016 (22% as of April 2016)
DAVAO ORIENTAL
Jct. Menzi-Dahican-Lawigan Tourism RoadLeads to Cinco Masao Beach Resort in the municipality of MatiNovmber 2016
Lupon Port, LuponExtension of reinforced concrete pier, construction of sea wall, expansion of back-up areaJune 2016
CAGAYAN
Replacement of Lucban Brudge and approaches along Manila North RoadConnects five major highways (Daang Maharlika, Cagayan Valley Road, Jct. Logac-Magapit Road, Bangag-Magapit Road, and Manila North Road)November 2016 (94.28% complete)
BATANGAS
Lobo-Malabrigo-San Juan RoadAn access road to the beaches in San Juan and LoboSeptember 2016
SAMAR
Gandara-Matuguinao RoadConcreting of road sections and slope protection worksSeptember 2016
Catablogan Port, CatbaloganPort improvementJuly 2016 (60.42% as of April 2016)
MISAMIS ORIENTAL
Butuan City-Cagayan de Oro-Iligan Road (BCIR) ProjectWill reduce travel time between Opol and Laguindingan; will provide additional access to the Laguindingan AirportNovember 2016
Widening of BCIR ProjectWidening of 16.92 kms of road sectionsNovember 2016
Jasaan Port, KimayaPort developmentAugust 2016
TARLAC
Tarlac-Pangasinan-La Union ExpresswayWil reduce travel time between Tarlac City and Rosales, Pangasinan; upon full completion, will also reduce average travel time between Tarlac City and Rosario, La UnionDecember 2016
BATAAN
Bagac-Mariveles roadWill provide a fast alternative route along the Subic-Morong-Bagac-Mariveles RouteDecember 2016 (22.5% complete as of April 2016)
BENGUET
Gurel-Bokod-Kabayan-Buguias-Abatan RoadWill lead to tourist destinations such as the Mt. Pulag and Kabayan Caves; will reduce average travel time between Brgy. Gurel, Bokod, and Brgy Abatan, Buguias; will serve as an alternate route to Mountain Province and IfugaoJuly 2016
ARMED FORCES OF THE PHILIPPINES MODERNIZATION AND CAPABILITY UPGRADE PROGRAM
PH Air Force – Two C-130 Aircraft units2nd unit to be delivered in the 3rd quarter of 2016
PH Air Force – Two Light Lift Aircraft (C-212) unitsTo be delivered within 2016
PH Army – 28 Armored personnel Carrier units14 units delivered; remaining units to be delivered within 2016
PH Navy – One 3rd Weather High Endurance CutterTo be delivered within 2016

2017

NCR
NLEX Harbor LinkWill connect MacArthur Highway in Valenzuela City and C3 in Caloocan City; will provide axxess to NLEX without passing through EDSA or the Balintawak Toll PlazaSeptember 2017 (24.42% complete as of March 2016)
Pasig Marikina River ChannelCovers the cities of Mandaluyong, Manila, Makati, and Pasig; will decrease flood inundation and reduce flood damageJune 2017 (56.84% complete as of March 2016)
Southwest Intermodal TerminalAn intermodal terminal for buses on the routes between Metro Manila and Cavite; will connect passengers from Cavite to other Metro Manila-bound transport modesNovember 2017
DAVAO DEL SUR
Cogon-Kapatagan-Mainit Tourist RoadWill lead to various tourist destinations such as Camp Sabros; will reduce travel tie between the city proper of Digos and Barangay CogonJanuary 2017 (70.31% complete as of April 2016)
Kapatagan-Tibolo RoadConcreting of a 6.02-km road sectionJanuary 2017
CEBU
Medellin-Daanbantayan RoadWill lead to Maya RORO Port, which serves as an access point to Daanbantayan’s beaches; will reduce average travel time between Barangay Maya and Cebu CityFebruary 2017 (20% complete as of April 2016)
BENGUET
Ballay-Tabio-Tonoman-Bulalacao-Tawangan-Lusod RoadWill serve as an alternate route to Tinoc, IfugaoMarch 2017
BOHOL
Panglao Airport Project, Panglao IslandWill serve as a replacement for Tagbilaran AirportDecember 2017 (2.43% complete as of January 2016)
ARMED FORCES OF THE PHILIPPINES MODERNIZATION AND CAPABILITY UPGRADE PROGRAM
PH Navy – Two Strategic Sealift vessels2nd unit to be delivered on May 2017

2018

NCR
C5 South Link ExpresswayWill reduce travel time from Taguig to Las Piñas/Cavite; will provide a direct, high-capacity route between the Makati and Taguig business districts to residential areas in Cavite, Parañaque and Las PiñasPhase 1 target completion in June 2018; Phase 2 target completion in December 2018
LRT Line 2 East Extension ProjectLRT-2 extension from Santolan, Pasig to Masinag, AntipoloFirst quarter of 2018 (16.38% complete as of April 2016)
ARMED FORCES OF THE PHILIPPINES MODERNIZATION AND CAPABILITY UPGRADE PROGRAM
PH Navy – Two Anti-submarine Warfare Capable HelicoptersTo be delivered within 2018
PH Air Force – Two Long-range Patrol Aircrafts
PH Air Force – Six Close Air Support Aircrafts

2019

NCR
NLEX Harbor Link Segment 8.2Will connect Mindanao Avenue to Commonwealth Avenue in Quezon City; will reduce travel time from Mindanao Avenue to Commonwealth AvenueFourth quarter of 2019
Metro Rail Transit (MRT) Line 7Development of an integrated ransport sysystem which involves a rail line from North Avenue, Quezon City to San Jose del Monte, Bulacan; an intermodal transport terminal (ITT) adjacent to the San Jose del Monte station; and a 6-lane road from NLEX Bocaue Interchange to the ITT2019
CEBU
Mactan Cebu Internatonal Airport New Passenger Terminal Building (PTB) Project, MactanConstruction of a new PTB; privatization of the airport’s operations and maintenance; renovation, expansion and rehabilitation of the existing PTBJune 2019 (6.68% complete as of January 2016)
ARMED FORCES OF THE PHILIPPINES MODERNIZATION AND CAPABILITY UPGRADE PROGRAM
PH Navy – Two Frigate unitsTo be delivered within 2019

2020

NCR
Light Rail Transit (LRT) Line 1 South Extension ProjectExtension of the LRT from Baclaran to Bacoor, CaviteFirst quarter of 2020

MULTI-YEAR COMPLETION

NCR
MRT Line 3 Projects

 

Procurement of 28 new light rail vehicles (LRV)Six LRV have been delivered as of April 2016; two more LRV deliveries targeted for May 2016
Procurement of long-term maintenance providerDecember 2018
Rehabilitation of rail, traction motors, signalling system, and conveyance facilities, among othersSecond quarter of 2017
ALBAY
New Bicol International AirportConstruction of runway, taxiway, apron, and perimeter fenceOctober 2016 (77% complete as of April 2016)
Site development and construction of landslide facilitiesMay 2018
Construction of passenger terminal buildingDecember 2018
BULACAN
Plaridel Bypass Road ProjectWill connect the NLEX in Balagtas, Bulacan and the Maharlika Highway in San Rafael Bulacan; will provide a faster route to San Rafael without passing through the town proper of Plaridel and the commercial areas of Pulilan and Baliuag along the Maharlika Highway; will cut travel time between Burol, Balagtas and Maasim, san RafaelMay 2018 (53.36% complete as of February 2016)
Bulacan Bulk Water Supply ProjectWill provide clean and affordable trated water to 22 water distracts in 21 municipalities and three cities in BulacanStage 1: July 2016 to July 2017; Stage 2: July 2017 to July 2018; Stage 3: 2020 to 2045
 ARMED FORCES OF THE PHILIPPINES MODERNIZATION AND CAPABILITY UPGRADE PROGRAM
PH Air Force – 12 FA-50 Aircraft units2017